production capacity calculation garments
Production Capacity Calculation in Garments
Capacity planning prevents over-commitment and improves delivery reliability.
Bangladesh-focused guide with practical calculation workflow.
Step-by-Step Explanation
- Input manpower and available time
- Set SMV and expected efficiency
- Calculate realistic output capacity
Formula Used
- Capacity/day = (manpower × working hour × 60 × efficiency %) / SMV
Example Calculation
- Manpower 60, hour 8, efficiency 75%, SMV 1.2 -> capacity 1,800 pcs/day.
Common Mistakes
- Using ideal 100% efficiency in planning
- Ignoring style learning curve
FAQ
- Should capacity be recalculated per style? Yes.
- Can overtime be included? Yes, as extra available minutes.