production capacity calculation garments

Production Capacity Calculation in Garments

Capacity planning prevents over-commitment and improves delivery reliability.

Bangladesh-focused guide with practical calculation workflow.

Step-by-Step Explanation

  • Input manpower and available time
  • Set SMV and expected efficiency
  • Calculate realistic output capacity

Formula Used

  • Capacity/day = (manpower × working hour × 60 × efficiency %) / SMV

Example Calculation

  • Manpower 60, hour 8, efficiency 75%, SMV 1.2 -> capacity 1,800 pcs/day.

Common Mistakes

  • Using ideal 100% efficiency in planning
  • Ignoring style learning curve

FAQ

  • Should capacity be recalculated per style? Yes.
  • Can overtime be included? Yes, as extra available minutes.