smv calculation for garments industry

SMV Calculation for Garments Industry

SMV is the core metric for target setting, manpower planning, and IE control in garments.

Bangladesh-focused guide with practical calculation workflow.

Step-by-Step Explanation

  • Measure basic operation time
  • Apply allowance percentage
  • Use final SMV in line planning

Formula Used

  • SMV = basic time + (basic time × allowance %)

Example Calculation

  • If basic time is 0.80 min and allowance is 20%, SMV = 0.96 min.

Common Mistakes

  • Using inconsistent allowance policy
  • Skipping method stabilization before SMV freeze

FAQ

  • Is SMV same as SAM? Often used similarly but verify factory definition.
  • How often should SMV be reviewed? After method/style changes.