SMV is the core metric for target setting, manpower planning, and IE control in garments.
Bangladesh-focused guide with practical calculation workflow.
Step-by-Step Explanation
- Measure basic operation time
- Apply allowance percentage
- Use final SMV in line planning
Formula Used
- SMV = basic time + (basic time × allowance %)
Example Calculation
- If basic time is 0.80 min and allowance is 20%, SMV = 0.96 min.
Common Mistakes
- Using inconsistent allowance policy
- Skipping method stabilization before SMV freeze
FAQ
- Is SMV same as SAM? Often used similarly but verify factory definition.
- How often should SMV be reviewed? After method/style changes.